You can get information on 40th Street from the City of
Tampa's special page on the project...CLICK
HERE
40th Street
Funding Takes Another Hit
(
http://www.tbo.com/southtampa/MGB5HJB6UPE.html ) reporter Kathy
Steele reveals that the City of Tampa has not been entirely honest with
us. After telling us they were $ 4 million short of the bid for
Segment B the article quotes Steve Daignault of the City of Tampa
stating that the segment is really $6 million short. Personally, I
am devasted. After trusting the city to get the project started as
promised, Segment B is now several months behind schedule with no relief
in sight. If you you can, please attend the MPO meeting on August
1st in the BOCC boardroom in the County Center at 9 a.m.
What's So Suspicious
About 40th Street and the City's Statements
Assuming that Daignault
is telling us the truth, that the project is now an $86 million dollar
project, the FDOT (federal and state) contribution is still 87.5% and
the county and city contribution is 12.5%. 12.5% of $86M is
$10,750,000, or $5,375,000 for each the county and city. Now the city
has already contributed some of their contribution for the McKinley
Road segment as well as monies for the ROW acquisition of Segments B
(totally acquired).
The County has given
the city, since 1998, about $4.5 million, nearly all of their half of
the money.
What this means is the
city should not have to contribute any more than $4 million total to
the rest of the entire project!!! And that’s based on $86 million
total cost for 40th Street.
Something is wrong.
The city is contributing money to other road projects. What happened
to the county’s contribution? Where is the city’s portion?
There is absolutely no
reason why Segment B should not have already started construction.
None whatsoever.
Council Wants Development
Restriction for Bayshore but Denies Same for 40th Street
http://southtampa.tbo.com/southtampa/MGBAWKA6UPE.html
ON July 20th City Council,
wanting to preserve Bayshore Boulevard, asked the City Attorney to
investigate restricting development there. The
40th Street Task Force has asked for the same kind of development
restrictions for years, until 40th Street is
completed...and told it is not
possible.
What is the Murphy Act and
TITFF's?
40th St Update
The
City of Tampa transportation department reported a single bid for
Segment B of 40th Street. This segment will probably be
the most expensive segment (from Hanlon Ave south to Hanna Ave) as it
requires not only straightening the road and widening it, but
completely replacing the bridge over the Hillsborough River. Although
they had placed a high estimate of $17 million on this segment the bid
came in at $21.7. Nevertheless, the Mayor claims that nothing will
impede the city moving forward with the project, even though we are
already three months behind schedule on beginning construction of
Segment B.
The nerve-wracking part of all of this is that since the bid is
higher than the current LAP the city must now revise the LAP with
approval from the MPO, FDOT, City Council and USDOT. I am concerned
that this will take longer than we can afford to wait so the more
pressure we can place on FDOT etal to move
this process forward the better.
In
addition to the construction of the road the City of Tampa Building
and Housing Services Department, lead by Cyndy
Miller, is working with the 40th St Task Force to create a
village feel with the new anticipated commercial and residential areas
along the corridor. Using CPTED and other methods they anticipate the
Temple Crest neighborhood to be a working model not only for the city
and state but the nation in regards to how to re-vitalize a community
and its’ transportation corridor with an emphasis on community instead
of focusing on the car. This is an exciting part of the project to
be moving towards.
Finally, I hope to see 40th Street completed soon as it
plays an important role in transporting people from northern areas of
Tampa to Ybor City and the Central Tampa core. We also provide a
continuous route to USF from these areas and because 40th
Street is an uninterrupted route from SR 60 we can plan HART routes to
transport students to USF from all over Tampa as well as provide
intermediate Park- N Ride areas for New Tampa and University Area
folks who want to go downtown.
Finally, our proximity to East Tampa and its’ revitalization and
Temple Terrace and its’ planned core downtown renovations, Temple
Crest has an opportunity to be a major player in the Near North area,
complementing, hopefully, the entire northeast area of Hillsborough
County.
Of
course I’m prejudiced, but since you’ve now seen my home, you’ll
understand why I want to preserve this jewel in the city of Tampa
while finding a way to connect it to other areas of the city.
Our
Sacrifices for the Sake of 40th Street (from the
Newsletter for July)
There
are written records of our neighborhood requesting improvements to 40th
Street since 1948. Now that we are finally seeing work beginning on the
project (knock wood) I think it is a good time to reflect upon what 40th
Street represents not just to the residents of this road but to the
neighborhood as well.
Everyone in Temple Crest is impacted by 40th Street. We must not only
drive on this road but the deterioration has affected our property
values, contributed to crime, all of which has caused the city to not
give a second thought to relocating section 8 and public housing
projects. Over the years our reputation as a desirable neighborhood has
suffered. The list goes on and on.
I
hope the residents of 40th Street appreciate that the entire
neighborhood has devoted countless hours to re-vitalizing the road. In
fact the neighborhood, in the hopes that improving 40th Street will
re-vitalize the entire area, has sacrificed as well.
Think
about it.
The
residents of 40th Street will have a beautiful corridor with new
sidewalks, drainage, sewers and water lines. Through numerous meetings
we have worked to help remove the TIPFF easements from their properties.
That’s what neighbors do for each other…we help, we look out for each
other.
As we
have fought for 40th Street improvements we have not fought as hard for
sidewalks in other parts of the neighborhood. We knew if we did it
might detract from our battle to improve 40th Street.
Much
of the neighborhood still has TIPFF easements on properties, including
my own. I could have fought to have our easement removed but I knew if
I did that it might impair progress on 40th Street.
Regnas and River Hills Drive need new sewer lines. But a fight for
these enhancements would have given the city reason to delay 40th
Street.
Yukon needs widening, it needs sidewalks. But if we fought for Yukon
would we have lost even more time for 40th Street? Of course it would.
The
neighborhood has stayed focused on 40th Street, primarily to the benefit
of a few residents and hopefully to the benefit of all of us, because I
know that fixing this road will fix many of the problems in our
neighborhood.
For
many years we have joined in charting a course of revitalization for
Temple Crest that finally is visible on the horizon. Sometimes that
means putting our own needs aside or at least resisting the temptation
to put our own needs first, for the greater good, for the needs of the
neighborhood.
50
years from now most of us will be gone from this earth. Hopefully, our
neighborhood will be a better place for what we are doing now.
Hopefully our legacy will be how we worked and sacrificed together to
create a better place for a few and an asset for us all.
40th St Update
SEGMENT B
I have just received this news from
Shannon Edge of the City of Tampa's Neighborhood Relations Department:
"Steve Daignault and Jean Dorzback asked me to forward to
you right away the attached FDOT Notice to Proceed Letter for the 40th
Street Segment B Project. Jean mentioned that "this letter gives us the
authorization that we have been anxiously awaiting to advertise and
award a bid to a contractor for this segment of 40th Street. The City's
Contract Administration Department is already working on this effort."
Read the
FDOT letter (Acrobat required)
As you all know I have always been cautiously optimistic about this
project and this development is certainly a step in the right direction.
Nevertheless, until I see the bulldozers... - Terry
Which name do you like for our 40th Street
community and economic center?
-
Temple
Crest Village
-
River
Rise
-
Temple
Ridge Village
-
River
Run
-
River
Esplanade
-
Hillsborough Glen
-
Hillsborough Quay
-
River
Quarter
-
River
Crest
-
River
Path
-
Terrace
Grove
-
River
Bluff
-
Terrace
Bluff
-
Hillsborough Crossing
40th St Update
I went to City Council to dispute
TECO's claims about buried utilities on 40th Street. Read the
article by Kathy Steele:
Resident Disputes TECO Estimate For Burial Of Lines
Assuming that
Daignault is telling us the truth, that the project is now an $86
million dollar project, the FDOT (federal and state) contribution
is still 87.5% and the county and city contribution is 12.5%.
12.5% of $86M is $10,750,000, or $5,375,000 for each the county
and city. Now the city has already contributed some of their
contribution for the McKinley Road segment as well as monies for
the ROW acquisition of Segments B (totally acquired).
The County has
given the city, since 1998, about $4.5 million, nearly all of
their half of the money.
What this means is
the city should not have to contribute any more than $4 million
total to the rest of the entire project!!! And that’s based on
$86 million total cost for 40th Street.
Something is
wrong. The city is contributing money to other road projects.
What happened to the county’s contribution? Where is the city’s
portion?
There is
absolutely no reason why Segment B should not have already started
construction. None whatsoever.